Flyovers & Junction Improvements where work is completed - Taloje
»
The proposed Taloja flyover is a part of Mega scheme of construction of 50 flyovers in Mumbai by M.S.R.D.C.
»
The flyover is situated at the Junction of Taloja on Sion Panvel Express
»
Contract for the execution of the poject work was awarded to M/s. Puri International Ltd.
»
Project Management of the project is being carried out by M/s. Shrikhande Consultsants (P) Ltd. Vashi Navi Mumbai.
Technical Aspects
Value of contract
Rs. 6.02 crores
Date of award of contract
14.8.1998
Date of commencement of work
16.8.1999
Stipulated period of completion
15 months including monsoon
Date of completion
13.11.1999
Actual Date of completion
23.10.99
Total Length of flyover
522 m
Carriageway
One carriageway of 11.00 m with crash barrier of 0.5 m each at either end providing a total deck width of 12.00 m.
Super structure
Precast prestress girder with RCC deck 9 span of 18.80 m each.
There are two obligatory spans of 30.00 m of prestressed cast - in - situ box girder.
The foundation on pile foundation 10 to 15 m depth done with rotary pile driving equipment.
The girder for super structure are casted at Casting yard near flyover bridge and are erected with the cranes and gantries.
Latest construction technique & modern machinery has been used in the construction which has resulted in completion ahead of scheduled date of completion.