MSRDC - Project - Improvement of Nagpur - Aurangabad - Sinner - Ghoti - Mumbai
Rd. to NH Standard |
|
|
|
|
|
|
|
PROJECT BACKGROUND |
|
|
|
Development of high-density corridors and establishing high-speed connectivity has
been on top priority of Government agenda. As a first step in this direction the
Government of Maharashtra has decided to develop and strengthen the linkages and
connectivity of major cities of state with Mumbai, the state capital.
|
|
|
|
Exploring the viability of one such connectivity of Nagpur with Mumbai, which includes
links –Butibori-Wardha – Karanja – Aurangabad – Sinner - Ghoti alongwith link from
Karanja – Loni - Nagzari corridor, was an endeavor in this direction.
|
|
|
|
IMPORTANCE OF THE PROJECT |
|
|
|
i. |
The length passes through backward regions of Vidarbha and Marathwada. |
|
ii. |
The distance from Mumbai to Nagpur will be reduced by 50 kms. |
|
iii. |
It will reduce travel time considerably and will be cost effective. |
|
iv. |
It connects Industrial places at Butibori, Amravati, Jalna, Chikalthana, Shendra,
Waluj, Sinner. |
|
v. |
It connects Tourist places at Karanja, Lonar, Sindkhedraja, Verul, Shirdi. |
|
vi. |
It will boost employment through development of Industries in backward regions. |
|
|
|
|
GOVERNMENT APPROVAL |
|
|
|
The Government of Maharashtra has accorded its consent to this project in the meeting
of Cabinet Committee for Infrastructure held on dated 23.12.1999.
|
|
|
|
The Government of Maharashtra had declared
MSRDC as an “Entrepreneur” for this project vide its resolution-dated 15.06.2002.
|
|
|
|
DETAILS OF PROJECT |
|
|
|
The total road length of proposed Nagpur – Aurangabad – Mumbai road is 700.00 Kms. |
|
|
|
Sr.No |
Name of Region |
Length(approx.) |
|
1. |
Vidarbha |
400 Km. |
|
2. |
Marathwada |
160 Km. |
|
3. |
Rest of Maharashtra |
140 Km. |
|
|
Total : |
700 Km. |
| |
|
|
|
| |
|
|
|
|
|
|
TOTAL SCOPE OF PROJECT |
|
|
|
The approximate length is 700 Km & Estimated cost Rs.700.00 crore. |
|
|
|
The corridor development is proposed to be National Highway Standard i.e.7.00 m.
wide Carriageway and embankment width at top i.e. roadway of 12.00 m.
|
|
|
|
Sr.No. |
Particulars |
Scope |
|
1. |
New Road construction |
128.43 Km. |
|
2. |
Improvement of existing road |
560.30 Km. |
|
|
Total : |
690.73 Km. |
| |
|
|
|
| |
|
|
|
|
|
|
EXECUTION OF WORK |
|
|
|
MSRDC has taken up the work of entire project in four main sections viz. |
|
|
|
1) |
Butibori to Karanja (188.66 Km.) |
|
2) |
Amravati – Nagzari – Kherda – Karanja – Malegaon – Mehekar (172.92
Km.) |
|
3) |
Mehekar – Sindkhedraja – Jalna – Aurangabad (121.39 Km.) |
|
4) |
Aurangabad – Vaijapur – Puntamba phata – Sinner – Ghoti. (202.37
Km.) |
|
|
|
|
These four sections are further divided in Nineteen Packages for construction Package
wise physical position of project is as below.
|
| |
|
| |
|
|
|
Package wise Position of Works (31/08/07) (Figure in lakh) |
|
|
Pac
No |
Name of Package |
Length
in Km |
Est.
Cost |
Expdtr. |
Present Position |
|
1 |
2 |
3 |
4 |
5 |
6 |
|
1 |
Buti Bori Wardha |
42.60 |
2449.93 |
2255.17 |
34.40 Km. completed |
|
Wardha Talegaon |
56.30 |
4750.60 |
4690.25 |
Completed |
|
2 |
Wardha Bypass |
11.30 |
1492.14 |
1473.10
|
In progress. |
|
3 |
Talegaon Shingnapur |
31.93 |
3142.50 |
2216.58 |
In progress. |
|
Shignapur Karanja |
49.65 |
3936.57 |
3793.98 |
Completed |
|
4 |
Bridges Bembala /Chandrabhaga Rivers |
2 Nos |
154.62 |
145.42 |
Completed |
|
5 |
Bridge Wardha |
1 Nos |
320.95 |
320.95 |
Completed |
|
6 |
Nagzari Karanja |
49.90 |
2811.08 |
3333.33 |
In progress. |
|
7 |
Karanja Malegaon |
78.00 |
7621.71 |
5547.52 |
In progress. |
|
8 |
Malegaon Mehkar |
45.00 |
941.07 |
909.29 |
Completed |
|
9 |
Mehkar Bypass
Mehkar Sultanpur
Sultanpur Dusarbid
Dusarbid- Dist Border
Bridges, CD works (Pck-IX)
Bridge in Km 26/035
Bridge Khadkapurna Km27/460 |
07.40
09.00
29.40
29.40
0.00
1 Nos
1 Nos
|
988.65
532.20
121.00
1062.73
2191.00
52.85
51.84
|
0.00
584.89
122.32
1132.69
0.00
35.24
59.88
|
LA in process 2nd Priority
Completed
Completed
Completed
Tender stage
In progress.
In progress. |
|
10 |
Buldhana Dist Border-Jalna |
17.00 |
1620.00 |
1109.33 |
In progress. |
|
|
Jalna Bypass Part A & B |
8.30 |
881.14 |
882.14 |
Completed |
|
11 |
Jalna –A’bad –4 Bridges
Shendra Chikalthana 4 Lanning
Zalta Bypass
Service Road Beed Bypass
Paithan link
|
4 Nos
8.00
4.00
11.30
4.65 |
176.00
601.00
437.61
1085.49
984.00
|
18.00 |
The work proposed to be
deleted as the work is being
taken by PWD. Under BOT
LA in process by CIDCO
IRDP-Aurangabad work |
|
12 |
Aurangabad-Lasur Station |
28.93 |
2452.00 |
2403.12 |
Completed |
|
13 |
Lasur Station-Vaijapur |
27.97 |
3580.00 |
1705.00 |
In progress. |
|
14 |
Vaijapur -Puntamba Phata |
31.27 |
3919.12 |
3848.58 |
Completed except 210 M. |
|
15 |
Godawari Bridge |
- |
370.00 |
376.68 |
Completed |
|
|
ROB @ Sawantsar |
- |
235.00 |
209.98 |
In progress. |
|
16 |
Puntamba Phata-Sinner
Zagde Phata-Sawli Vihir |
49.00
06.00 |
4582.00 |
0.00 |
Tender Stage
Second Priority |
|
17 |
Sinner Bypass |
8.34 |
3 |
3 |
LA in progress 2nd priority |
|
18 |
Sinner Ghoti |
50.00 |
3 |
3 |
Work Completed. |
|
19 |
Ghoti Bypass & ROB |
1.20 |
3 |
3 |
Tender stage. |
|
|
Total: |
639.54 |
60393.58 |
45089.98 |
|
|
|
|
|
|
|
|
|
|
|
Physical Progress of the Project |
|
|
|
Physical Progress of the Project |
|
Presence scope of work and Cumulative Physical Progress |
|
Total scope of work |
Completed |
In progress |
To be taken |
|
Road |
668.69 Km. |
494.15 Km. |
68.60 Km. |
105.94 Km |
|
CD work |
788 |
611 |
10 |
166 |
|
Slab drain |
33 |
34 |
- |
- |
|
Sub way |
6 |
5 |
- |
1 |
|
Minor bridge |
220 |
147 |
3 |
70 |
|
Major bridge |
16 |
14 |
- |
2 |
|
ROB |
3 |
- |
2 |
1 |
|
|
|
|
|
|
|
|
|
Project Management Consultant.(PMC) |
|
|
|
Package No. |
Name of Package |
Name of the PMC |
|
I, II, V
|
Butibori to Talegaon Wardha Bypass |
M/s. Lea Associates South Asia Pvt. Ltd., India (LASA), New Delhi. |
|
III & X |
Talegaon to Karanja Buldhana Dist. Border |
M/s. Gherzi Eastern Pvt. Ltd., Mumbai |
|
VI, VII VIII |
Loni – Karanja – Malegaon – Mehekar |
M/s. CES (I) Pvt. Ltd., Mumbai. |
|
XII, |
Aurangabad to Lasur |
M/s. Span Consultants, New Delhi. |
|
XIII |
Lasur to Vaijapur |
M/s Technogem Consultants Mumbai |
|
XIV, XV, XVI |
Vaijapur to Sinner |
M/s. Sungrace Engineering Projects, Pune |
|
XVII, XVIII, XIX |
Sinner to Ghoti |
M/s. Frischmann Prabhu (I) Pvt. Ltd. |
|
IV |
Bridges |
P.W.D. |
|
|
|
|
Contributions from Government |
|
|
|
The Government agreed to contribute to the extent of Rs.150.00 Crore. @ Rs.30.00
Crore per year for construction and Rs. 9.00 Crore for land acquisition. The contributions
received up till now are as below: –
|
|
|
|
|
2000 – 2001 |
– |
Rs. 22.95 Cr. |
|
|
|
2001 – 2002 |
– |
Rs. 12.46 Cr. |
|
|
|
2002 – 2003 |
– |
Rs. 05.17 Cr. |
|
|
|
2003 – 2004 |
– |
Rs. 03.08 Cr. |
|
|
|
2004 – 2005 |
– |
Rs. 03.07 Cr. |
|
|
|
2005 – 2006 |
– |
Rs. 0.00 Cr. |
|
|
|
2006 – 2007 |
– |
Rs. 2.49 Cr. |
|
|
|
Total |
– |
Rs. 49.22 Cr. |
|
|
|
|
|
Toll Stations |
|
|
|
Total 13 toll stations are proposed in the throughout length at various locations.
Out of these 13 toll stations collection of toll is started at 8 toll stations Remaining
5-toll stations toll collection is yet to be started.
|
|
|
|
|