MSRDC - Project - Nandurbar Integrated Road Development Project
Present Status
 
Name Of Work Est. Cost Bid Cost Name of Contractor Date of Starting Date of Completion Expenditure Physical Progress
Construction of ROB on LC 90C 8.47 Crores 7.88 Crore M/s Vijay Nirman Co.,Nagpur 30.7.04 15.8.06 5.37 Crore Except Railway portion other works upto girder completed. Out of 16 deck slab 10 deck slab are completed
Construction of ROB on diversion road 3.17 Crore 3.05 Crore M/s Vijay Nirman Co., Nagpur 19.8.04 31.5.06 0.96 Crore Subway is completed Except Railway boundary 132 m 90% work is completed
Improvement to diversion road (7.2 km) 1.90 crore 1.59 + 0.78 = 2.37 Crore M/s H.A. Vora 23.12.02 31.7.04 2.55 Crore Completed
Improvement to internal roads (13.5 km) Not Yet Started